Activity Reports
All Team members can report progress on the activities they
have
been assigned and provide notes regarding status.
To do this, click Report>Activity
Report, Goal
Director will open a dialogue box, giving you the option of selecting
the
year and week to report. The week you are currently in is the default
week. (you may also report for others by selecting that
person's name under Person in the drop-down menu.)
After you have chosen a year and week for the report, a
window will pop up with only the activities that the person is
scheduled to
work on during the period you have selected. At the far
right of the window you may view activity information such as the
scheduled finish date and original
estimates. You may customize the view by clicking on View>Personal Activity Report and
then select options.
Activity report fields
You may report the following information in the columns in
the left area of the window:
Work Done
Here you may report the total number of hours or days you have
worked
in the period. If you wish to report on your work accomplished each day
of the week instead of for the entire week, you may click View>Personal activity
report>Show
Weekdays.
Work to do
This is the amount of time, in hours and days, that you
estimate will be required to complete the activity.
On schedule
Enter a Y or N according to whether or not you will make the
scheduled finish date.
Quality accepted
Enter a Y or N according to whether or not the quality of
the work you have done is good enough.
Responsibility Chart kept
Enter a Y or N according to whether or not people worked on
the activity according to the responsibility chart.
Changes Req.
Enter a Y or N according to whether or not modifications were
necessary on the work you have accomplished.
Waiting time
Enter a Y or N according to whether or not you were required
to wait
for other people to complete their tasks before you could start or
continue your work.
Special problems
Enter a Y or N according to whether or not special problems
have arisen. The text field under is available for expanded
descriptions.
Delay
Report delays for the activities.
Accumulated
This column shows the sum of prior reported hours, days, weeks
or month.
Annotating the report
For example, if you report N for the field On Schedule,
Goal Director
shows this in a red color. You may annotate any of the Y or N
answers in the following way:
- Click on Add in
the lower right area of the window
- Give the annotation a description name.
- Type your comments in the fields: Description, Cause,
Consequence,
Action.
- Highlight the Y or N field you wish to annotate.
- Click on Link to
connect the annotation.
Comments can be deleted or given a new name by highlighting
the
comments and clicking on Delete or Rename.
If you wish to delete a connection you already have created,
you can
highlight the report field and click on Unlink.
Viewing Activity Report options
Sort by
The activities are iniitially shown and sorted by activity code. You
can show and sort by the full identity of the activities by
clicking View>Personal activity
report>Sort by>Project, Milestone Plan,
Milestone...
All : Shows all activities you are scheduled to work
on, in every time period.
Ongoing: Shows all activities you are working on in the
current period.
Ongoing and recently worked on: Shows all activities
you
are working on in the current period plus the activities you worked on
in the previous period (week).
When all team members have created their Activity reports, Project
Leaders and others can then create an overall report agregating those
individual activity reports by clicking Report>Agregate. It will
show the agregate total work
hours, remaining work and all the annotations of problems or issues on
specific activities.
Printing the Personal Activity Reports
You can choose print properties to control: time period,
Gantt display, Codes, Revised dates, Responsibility
codes, Estimates, or Both.
Click Ok to print.
Printing, Previewing, Making
.GIF files
Throughout Goal Director, you can print reports to either a
printer, screen or a .gif file that can be put into other
applications
(for example Word, Notes etc.) If you want to send a report to a
printer, click the Printer icon in
the toolbar. If you want to preview on the screen, click the Print Preview icon in the toolbar.
If you want to make a .gif file click on Copy in the Print Preview toolbar
to save it to a subdirectory of your choice.
Email Activities
You can Email the activities defined for a project to a
person. To Email them, click Report>Mail
activities.
Email Timesheet
You can Email a timesheet to a person. For example, you
can send it to a person who will enter
it into the administrative system. To Email it, click Report>Mail timesheet.
Aggregate Report
Project Leaders can create a total project report by
agregating all Activity Reports submitted by all team members working
on the project. This report enables a project leader to consider
annotations made by team members, and make necessary decisions.
These reports may
also be used to provide overall progress information to oversight
groups.
Report types:
Aggregate reports can be summarized at the following levels:
- Activity level
- Milestone level
- Project level
Aggregate reports are run by clicking Report>Aggregate.
The dialogue box shown below enables you to choose which type of report
and which time interval you want to run. You can also update existing
reports by checking Regenerate
existing reports.
Click on Start to
create the aggregate report.
After Goal Director has finished aggregating your report, a
dialogue box
will pop up (see below) telling you if a New report has been saved and
for which Milestone. To view a report, highlight the desired
report and click on the button Open
Report. The
reports are saved under the indicated Milestone in the project tree
corresponding to the report's
level.
Deleting reports
All reports that have been printed
out are kept to maintain a project report history. It is,
however, possible to delete reports by right clicking on the report in
the
project tree and clicking Delete.
Below is an example of an Aggregate Activity Report that shows the
agregated status and annotations reported by all people who submitted
activity reports for the various
activities for the selected period of time.
Printing the report
You can choose print properties to control: time period, whether to
display the Gantt, Codes, Revised dates, Responsibility codes,
Estimates, or Both.
Click Ok to print out..
Printing, Previewing, Making
.GIF files
Throughout Goal Director, you can print reports to either a
printer, screen or a .gif file that can be put into other
applications
(for example Word, Notes etc.) If you want to send a report to a
printer, click on the Printer icon in
the toolbar. If you want to preview on the screen, select the Print Preview icon in the toolbar.
If you want to make a .gif file click on Copy in the Print Preview toolbar
to save it to a subdirector of your choice.
Accumulated work done
The accumulated work done report shows work done pr person for
the
selected projects, persons, on different levels. To open the
Accumulated work done report, click Report>Accumulated work done.
You may select other projects to as well by clicking on the
project name and the the button Load
data
Projectportfolio
The projectportfolio is an overview of the selected projects
timeframe(start- and finishdate) in a Gantt format. The deviation
between the
finishdate and revised date is printed in red. To open the
projectportfolio, click Report>Portfolioreports>Projectportfolio
Revised Milestone Plan
Based on the information you have accumulated from your
project team members, and aggregate reports, you may need to revise the
Milestone Plan. This is done by clicking on Report>Revised Milestoneplan.
When you choose to revise a milestoneplan, a dialogue box will
open for
you to enter the year and week that the revision is to be made.
You may enter a Revised date, Report text, and the date of the
revision in the column entitled "Reported" for any milestone.
Printing a Milestone plan
report
You will be given several options regarding the format of the
report (see below)
Click Ok to print.
Extending Milestoneplan or Milestone Activities finish dates
To report on ongoing activities that are beyond the the
planned finish date, you must extend the finish dates.
To extend the finish dates for all activities belonging
to a milestone
or all activities belonging to a milestoneplan, click Tools>Displace activity dates and select the
Milestoneplan, or specific Milestones and the number of days to
displace.
Project description
Project description is a printout of all the different
properties of
the project, selected by year.
The report contains:
- Project Properties
- Responsible persons
- Timeframe
- Budget
- Mandate
- Milestoneplans
To print this report open the project, then highlight the
project name
and click Report> Project description
No preview is available for this printout. It is sent directly to the
printer.
Statusreports
Status report by the Project leader
People who are the designated Project Manager in Project Properties
have the option of reporting monthly progress and
status on their projects. click Report>Status Report>Project
leader and select the month and year you want to make the report
for.
The report will include projects where the report month falls within
the project start and finish dates as defined in the project
properties.
The following fields are editable by the Project Manager:
Date changed: Proposed new finish date.
Proposed change to the finish date will not be updated in
the project properties, plans or budget.
These changes must be updated manually in the Project
properties.
Planned status: Narrative
Actual status: Narrative
Cost change: Proposed
change to the cost will not be updated in
the budget.
This changes must be updated manually in the Project property>Budget
dialogs.
Progress evaluation: select from pre-defined drop down list
box options
Status and comments on deviation
Revision: Date or number of this Status report
The report will initially show the last months revision number
to help the
project leader select a new revision number for the new report.
(the revision field will be empty until the first report has been
saved)
The data in this status report is included in the Progress
report (see below)
Status report for Program Managers
People who are the designated Program Manager in Project Properties
have the option of reporting status on their projects. click Report>Status
Report>Progran manager and select the year and tertial period
you want to make the report
for.
This report displays only the projects where:
- the logged on person has status as Program Manager(defined in project
properties).
- the report period falls within the project's timeframe as defined in
the project properties dialog (start and finish dates).
The program manager can approve/reject a Project Leader's
suggestion for
cost
change, by editing the field Funding change(+/-).
To view the report on screen, click the print preview icon
in the toolbar.
Progress report
Progress report is a printout containing:
- Project Properties
- Budget status
- Progress
This report is generated using data from the Project
Leader's Status Report
To generate
this printout you must have created a Project Leader Status report on
at least one project, and have one of your projects opened.
Click on Report> Progress
report.
In the dialog choose the report period and the project you
want the
report
for.
Only projects of the logged on Project Leader are
shown.
Resource Extract (overview of planned and actual resources)
You can get a report of the estimated, comleted, and future
resource utilization by clicking Report>Extract.
The
Resource Extraction may filtered per the drop-down listboxes below.
You have the option of sorting the information by activity
or person
If you check Include Totals, you will be given sub-totals for
the levels you have chosen for sorting.
To generate the report, click Load data
Below is an example of a Resource extract report.
In the example, we have created an overview of all projects
and the
person Christian Wahl for Weeks 24 through 31 of 2001. In the gantt
area, Goal Director shows 3 resource numbers for the activity: The top
number shows the reported Work done (actual completed), the middle
shows how much Work remains to be done, and the bottom number shows the
original estimate
Sub-totals are given for every milestone plan:
The bottom of the report shows the Totals for the
person and the selected project(s).
Budget Report
To print a Budget Report, highlight either a Project,
Milestone Plan or Activity Plan, the click on Report>Budget Report.
This report gives an overview of the
following:
- Estimates (estimates from Activity
Responsibility charts)
- Completed (the work hours that the project team members
have
reported as completed)
- Deviation (estimates vs. completed hours)
- Remaining (the work that hours the project team members
have
reported as remaining)
- Prognosis (the sum of hours completed and the reported
remaining hours)
- Total (the original estimate minus the prognosis for
completion)
The report below can be viewed on the screen by clicking Print
preview icon or sent to the printer by
clicking on the Print icon in the toolbar.
Budget Graph
To create a graphic presentation of the progress of the
project,
milestone plan or milestone, click Report>Budget
Graph.
The graph contains the following:
- Estimates (estimates from Activity Responsible
charts)
- Completed (the work hours the project team members have
reported as completed)
The report can be viewed on the screen or a sent to a printer
by
clicking on the appropriate icon in the toolbar.
S-Curve
To create a graphic presentation of the progress of the
project,
milestone plan or milestone including the prognosis, click Report>S-Curve. The graph
contains the following:
- Estimates (estimates from Activity Responsible
charts)
- Completed, in blue (the work hours that the project team
members have reported as completed)
- Prognosis, in green (the sum of hours completed and the
reported remaining hours)
The report above can be viewed on the screen or sent to
the printer
by
clicking on the appropriate icon in the toolbar.
Email Activities
If some team members do not have access to Goal Director, you
can e-mail the activities to them. This is accomplished by choosing Report>Mail Activities.
Goal Director sends all the activities listed under the
open project to the specified participant.
Tools
Selecting Language
From the Tools menu you can choose the language you want to
use for the
taskcodes and printouts presented on your machine or the language for
the
entire application. The language you select will be utilized in all
projects.
You switch languages by clicking Tools>Language and select
the language you want. To change the application language, you must
restart Goal Director to activate the changes.
Click Ok and you have changed the language according to your
choice.
Defining Criterias
A project can be classified by using predefined criterias. Valid
criterias
are defined by clicking Tools>Criterias.
The following criterias are available:
- Businessarea
- Project Program
- Project Status
- Project Type
- Evaluation Status
- Progress Evaluation
Add
Click Add button, fill in
criteria and click Ok to save.
Delete
Highlight the criteria you want to delete, and click Delete button.
Edit
Highlight the criteria you want to edit, and press Edit. Make changes,and
press Ok to save.
Checking-out and Checking-in projects
You have the option to work on your project in a local
database on your workstation or laptop computer. This function allows
you to check-out
one project per client from the project database ("library"). When you
check-out a project from the server it locks the project, so that no
one else can make changes to the same project before you have checked
it in again. Note: When you check-out a project,
previously checked-out projects on your local machine will be deleted..
Check-out project
To check-out a project, click Tools>Check-out
project. Goal Director will dowload the project to your local
database.
Check-in project
To upload the project to the server click Tools>Check-in project.
Undo Check-out project
Click Tools>Undo Check-out project.
If you
made changes to the project on your local computer you will lose any of
those changes.
Preferences
Click Tools>Preferences
Under the General tab, you have the following choices:
- 4 chars in year
= all date formats
in the application will display the year as 4 numbers (YYYY).
- Small font in printout
= all printouts
will have an 8 pt. font.
- Preview in Landscape
= all previews
will show up in the Landscape format.
- Preview in A3 = all
previews will be
shown in A3 format.
- Show the
organisation-abbrevition as a person-prefix = you will be able
to search for persons within
organisations
- Auto resize the width of
the taskcodes table = all responsibility charts will
automatically adjust the size of the frame for roles/persons.
- Default timescale =
Set the estimating unit as the default
throughout Goal Director.
- Default gantt scale
= Set the gantt scale as the default throughout Goal Director.
Under the E-mail tab, you have the following choices:
- E-mail Address =
your own standard e-mail address. Must be
added under resource menu.
- SMTP Server Host =
the name of your email server
- Port = the port you
use for mail
- Timesheets = the
initial e-mail address you want Goal Director to display when you
want to email your timesheets.
- Activities = the
initial e-mail address you want Goal Director to display when you want
to email all project activities.
Under the Server tab, you have the following choices:
- Server Hostname =
Enter the Goal Director server's computer name (as recognized by the
network) or its IP
address.
- Server Port Number
= You can specify which port
Goal Director will use when being run as an application applet.
The default is 1099.
Connected users
You can find out which other users are connected to the Goal
Director server by clicking Tools>Connected
Users.
Goal Director displays the
users who are connected so you can send them a message to quit Goal
Director.
Administration of Roles, Organizations and People
Roles
The Principle chart and Milestoneplan Responsibility charts
use Roles (skills, groups) as defined for the
organization. Click on Resource>Roles
or Ctrl+Shift+R. A window will pop up with options to Add new roles, Delete or Modify existing roles. You can also
add new Roles while you are working with the Principle chart or
Milestone Responsibility charts.
Organizations and Units
You may classify roles and persons by Organizations and
Units. Click
Resource>Organizations/Units or Ctrl+Shift+O
In the example below, you see that we have set up several
organizations. New organizations are set up by clicking on New and
entering the name of the organization you want to set up.
You may define Units within Organizations. Highlight the
organization, click on New and
enter the name of
the new unit.
You may also include predefined role(s) in an organization and
unit by doing the following:
- Highlight the organization and unit
- Highlight role(s) and click on >> to include those roles
Persons
Defining persons in the organization is done by clicking Resource>Persons or
Ctrl+Shift+P.
Goal Director will generate a dialogue box containing persons
who have already been defined (eg. Supervisor). Those persons
with full login privileges are shown in boldface type. To add a new
employee,
click on Add.
When adding a new employee, the following information should
be filled in:
- Name : First and last names
- Initials : Unique combination of letters, usually
First letter of the first and last names
- E-mail : The person's e-mail address
- Username : If using Windows NT, the user name can be
the same as the one for logging-on to the machine
- Password : The password that the person will need to
supply during log-on.
- Usergroup : User level access control as defined on
the server
- Organization : The organizational entity the
person belongs to (selected from drop-down list)
- Unit : The unit entity the person belongs to
(selected from drop-down list)
- Roles : The role(s) the person has, or belongs
to
All information entered for the person can be modified or
deleted at any time by highlighting the person in the initial pop-up
dialogue and clicking Modify
or Delete.
When you are finished updating persons, click Close.
Copying the Database
CAUTION:
The following functions should only be used by experienced users.
They can cause your existing database to be overwritten.
Alternatively,
you may use your operating system's file copying functions to achieve
similar results.
In any case,
you should back up your database on a regular basis.
This function gives you the ability to copy the database you
are working with, or select another database
to work with. Before you log on to Goal Director, you will see the
function File>Copy Database
under the File menu. If you are already working
with Goal Director, choose Log Out under the File menu and Copy
Database
will be archived.
When you have chosen Copy Database, the following dialogue box
will pop up.
If you choose to save the database to a file, your current
database will be saved to the named file. From that location, it
can be used as an alternate database, either by you or other Goal
Director
users.
The following specific function must
be used with caution.
If you wish to save a database other than your existing database to an
alternate location, highlight Choose File, which
will become the database. Before you execute this function, it is
highly recommended that you make a copy
of your existing database, so as to prevent any loss of
information. It can
cause your existing database to be overwritten.
|